NYC Resources311Office of the Mayor

Official Website of the New York City Department of Parks & Recreation

Hansborough Recreation Center Gym Floor and Window Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the gymnasium floor and natatorium windows at the Hansborough Recreation Center.

Project Timeline

Design

Start Date: December 2013
Projected Completion Date: March 2015
Completion Date: June 2015

Procurement

Start Date: June 2015
Projected Completion Date: March 2016
Completion Date: July 2016

Construction

Start Date: October 2016
Projected Completion Date: October 2017
Completion Date: November 2017

Understand how we build parks.

Funding

Total Funding: $415,000
Funding Source: City Council

Location

Hansborough Recreation Center , Manhattan
35 West 134th Street, Manhattan

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 05/24/2018

Was this information helpful?