Owen Dolen Recreation Center Roof Reconstruction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct the roof and exterior walls at the Owen Dolen Recreation Center in Owen Dolen Park.

Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.

Project Timeline

Design

Start Date: September 2013
Projected Completion Date: May 2015
Completion Date: January 2017

Procurement

Start Date: January 2017
Projected Completion Date: October 2017
Adjusted Completion Date: November 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

Owen F. Dolen Park , Bronx
2551 Westchester Avenue

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 08/17/2018