Owen Dolen Recreation Center Roof Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    40% complete

This project will reconstruct the roof and exterior walls at the Owen Dolen Recreation Center in Owen Dolen Park.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: September 2013
Projected Completion Date: May 2015
Completion Date: January 2017

Procurement

Start Date: January 2017
Projected Completion Date: October 2017
Completion Date: December 2018

Construction

Start Date: April 2019
Projected Completion Date: April 2020

Understand how we build parks.

Funding

Total Funding: $2,390,000
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

Owen F. Dolen Park , Bronx
2551 Westchester Avenue

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 01/27/2020