Citywide Retaining Walls and Seawalls Reconstruction (CNYG-514M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    29% complete

This project will reconstruct and stabilize retaining walls and seawalls in parks citywide.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: October 2013
Projected Completion Date: December 2013
Completion Date: January 2014

Procurement

Start Date: January 2014
Projected Completion Date: October 2014
Completion Date: May 2015

Construction

Start Date: May 2015
Projected Completion Date: November 2017
Adjusted Completion Date: September 2020

Understand how we build parks.

Funding

Total Funding: $26,207,000
Funding Sources:
  • Mayoral
  • City Council

Locations

 

Project Staff

Project Liaison: Contact Us
Contact NYC Parks about this project

Last updated: 10/11/2019