Dr. John's Playground Paths, Water Supply & Drainage System Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    58% complete

This project will reconstruct the paths, water supply and drainage systems at Dr. John's Playground.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: July 2011
Projected Completion Date: October 2014
Completion Date: January 2016

Procurement

Start Date: January 2016
Projected Completion Date: October 2016
Completion Date: December 2016

Construction

Start Date: April 2017
Projected Completion Date: April 2018

Understand how we build parks.

Funding

Total Funding: $2,682,000
Funding Sources:
  • Mayoral
  • City Council

Location

Marine Park, Brooklyn
Gerritsen Avenue and Avenue X, Brooklyn

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/20/2017