Glenwood Playground Synthetic Turf Field Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a multi-use synthetic turf field, adult fitness area, and sitting area, and reconstruct the handball courts and basketball courts at Glenwood Playground.

Project Timeline

Design

Start Date: December 2012
Projected Completion Date: April 2015
Completion Date: June 2015

Procurement

Start Date: June 2015
Projected Completion Date: March 2016
Completion Date: January 2016

Construction

Start Date: April 2016
Projected Completion Date: April 2017
Completion Date: April 2017

Understand how we build parks.

Funding

Total Funding: $2,500,000
Funding Sources:
  • Borough President
  • City Council

Location

Glenwood Playground , Brooklyn
Farragut Road and Ralph Avenue

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/15/2019