Lincoln Terrace Park Netball Court and Seth Low Playground Athletic Court Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the netball and handball courts at Lincoln Terrace Park and the perimeter paths, basketball and handball courts at Seth Low Playground.
Project Timeline
Design
Start Date: August 2013
Projected Completion Date:
November 2013
Completion Date:
June 2014
Procurement
Start Date: June 2014
Projected Completion Date:
March 2015
Completion
Date:
June 2015
Construction
Start Date: August 2015
Projected Completion Date:
August 2016
Completion
Date:
August 2016
Understand how we build parks.
Funding
Funding Sources:
- Mayoral
- Borough President
- City Council
Locations
-
Lincoln Terrace / Arthur S. Somers Park, Brooklyn
Eastern Parkway, East New York Avenue between Rochester Avenue and Portal Street -
Seth Low Playground/ Bealin Square, Brooklyn
Avenue P, Bay Parkway, West 12 Street
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 06/28/2022