Schmul Park and Dugan Playground Ballfield Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the ballfields in Dugan Playground and Schmul Park.

Project Timeline

Design

Start Date: November 2013
Projected Completion Date: May 2014
Completion Date: July 2014

Procurement

Start Date: July 2014
Projected Completion Date: April 2015
Completion Date: January 2016

Construction

Start Date: March 2016
Projected Completion Date: September 2017
Completion Date: June 2017

Understand how we build parks.

Funding

Total Funding: $1,538,000
Funding Sources:
  • City Council
  • Federal
  • Mayoral

Locations

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 09/26/2022