Queensbridge Park Field House Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    93% complete

This project will construct a field house in Queensbridge Park.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: September 2014
Projected Completion Date: March 2016
Completion Date: February 2017

Procurement

Start Date: February 2017
Projected Completion Date: November 2017
Completion Date: December 2017

Construction

Start Date: January 2018
Projected Completion Date: July 2019
Adjusted Completion Date: October 2019

Understand how we build parks.

Funding

Total Funding: $6,378,000
Funding Sources:
  • Mayoral
  • City Council

Location

Queensbridge Park , Queens
Vernon Boulevard between the Queensboro Bridge and 41st Avenue

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 11/13/2019