Canarsie Park Comfort Station Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will construct a comfort station in Canarsie Park.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: January 2015
Projected Completion Date: September 2015
Completion Date: May 2017

Procurement

Start Date: May 2017
Projected Completion Date: January 2018
Completion Date: September 2018

Construction

Start Date: March 2019
Projected Completion Date: August 2020

Understand how we build parks.

Funding

Total Funding: $2,711,000
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

Canarsie Park , Brooklyn
Seaview Avenue and Paerdegat Avenue North

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/14/2018