Di Gilio Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Di Gilio Playground.

Project Timeline

Design

Start Date: August 2013
Projected Completion Date: September 2014
Completion Date: December 2015

Procurement

Start Date: December 2015
Projected Completion Date: August 2016
Completion Date: December 2016

Construction

Start Date: April 2017
Projected Completion Date: April 2018
Completion Date: May 2018

Understand how we build parks.

Funding

Total Funding: $2,859,000
Funding Sources:
  • Mayoral
  • City Council

Location

DiGilio Playground , Brooklyn
McDonald Avenue and Avenue F

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 01/21/2019