Joyce Kilmer Park Perimeter Fence Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a steel perimeter fence in Joyce Kilmer Park.

Project Timeline

Design

Start Date: November 2013
Projected Completion Date: June 2014
Completion Date: July 2015

Procurement

Start Date: July 2015
Projected Completion Date: April 2016
Completion Date: February 2017

Construction

Start Date: March 2017
Projected Completion Date: March 2018
Completion Date: March 2018

Understand how we build parks.

Funding

Total Funding: $679,000
Funding Sources:
  • Borough President
  • City Council

Location

Joyce Kilmer Park , Bronx
Grand Concourse between East 161st and East 164th Streets

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 08/17/2018