Pelham Bay Park Ballfields 4 & 5 Lighting Reconstruction

  • Design
    100% complete 
  • Procurement
    100% complete 
  • Construction
    90% complete 

This project will reconstruct the electrical feeders and conduits at ballfields 4 and 5 in Pelham Bay Park.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: July 2013
Projected Completion Date:March 2014
Completion Date: October 2014

Procurement

Start Date: October 2014
Projected Completion Date:July 2015
Completion Date: August 2015

Construction

Start Date: January 2016
Projected Completion Date:January 2017

Understand how we build parks.

Funding

Total Funding: $962,000
Funding Source:Mayor

Location

Pelham Bay Park, Bronx
Middletown Road and Bruckner Boulevard, the Bronx

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 01/13/2017