Midland Beach and Oakwood Beach Emergency Berm Installation

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a temporary emergency protective berm at Midland Beach from New Dorp Lane to Ocean Breeze Park.

Project Timeline

Design

Start Date: May 2013
Completion Date: October 2013

Procurement

Start Date: October 2013
Projected Completion Date: July 2014
Completion Date: March 2014

Construction

Start Date: November 2013
Projected Completion Date: February 2014
Completion Date: April 2014

Understand how we build parks.

Funding

Total Funding: $5,436,000
Funding Sources:
  • Mayoral
  • Federal

Locations

  • Franklin D. Roosevelt Boardwalk and Beach , Staten Island
    Between Graham Boulevard, Jefferson Avenue, Father Capodanno Boulevard
  • Great Kills Park , Staten Island
    East of Cedar Grove Avenue, between New Dorp Lane and Kissam Avenue. (New Dorp Beach, Cedar Grove Beach and Oakwood Beach)
 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 10/18/2019