Vietnam Veterans Plaza Reconstruction (Hurricane Sandy)

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct lighting and electrical components damaged by Hurricane Sandy at Vietnam Veterans Plaza.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.

Project Timeline

Design

Start Date: June 2015
Projected Completion Date: June 2016
Completion Date: February 2019

Procurement

Start Date: February 2019
Projected Completion Date: October 2019
Adjusted Completion Date: March 2021

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Sources:
  • Mayoral
  • Federal

Location

Vietnam Veterans Plaza , Manhattan
South Street between Broad Street and Old Slip

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 12/02/2020