Vietnam Veterans Plaza Reconstruction (Hurricane Sandy)

  • Design
    100% complete
  • Procurement
    40% complete
  • Construction
    0% complete

This project will reconstruct lighting and electrical components damaged by Hurricane Sandy at Vietnam Veterans Plaza.

Project Update: The solicitation documents have been issued to contractors, and Parks is awaiting the submission of bids.

Project Timeline

Design

Start Date: June 2015
Projected Completion Date: June 2016
Completion Date: January 2018

Procurement

Start Date: January 2018
Projected Completion Date: October 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Sources:
  • Mayoral
  • Federal

Location

Vietnam Veterans Plaza , Manhattan
South Street between Broad Street and Old Slip

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 09/21/2018