Vietnam Veterans Plaza Reconstruction (Hurricane Sandy)

  • Design
    100% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct lighting and electrical components damaged by Hurricane Sandy.

Project Update: Design is complete.

Project Timeline

Design

Start Date: June 2015
Projected Completion Date: June 2016
Completion Date: January 2018

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Sources:
  • Mayoral
  • Federal

Location

Vietnam Veterans Plaza, Manhattan
South Street between Broad Street and Old Slip, Borough of Manhattan

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 01/18/2018