Tappen Park and South Beach Fountain Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    4% complete

This project will reconstruct the electrical and mechanical components of fountains damaged during Hurricane Sandy at Tappen Park and South Beach.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: July 2015
Projected Completion Date: June 2016
Completion Date: June 2017

Procurement

Start Date: June 2017
Projected Completion Date: March 2018
Completion Date: February 2020

Construction

Start Date: September 2020
Projected Completion Date: September 2021

Understand how we build parks.

Funding

Total Funding: $2,290,000
Funding Sources:
  • Mayoral
  • Federal

Locations

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 11/25/2020