Tappen Park and South Beach Fountain Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the electrical and mechanical components of fountains damaged during Hurricane Sandy at Tappen Park and South Beach.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: July 2015
Projected Completion Date: June 2016
Completion Date: June 2017

Procurement

Start Date: June 2017
Projected Completion Date: March 2018
Completion Date: February 2020

Construction

Start Date: September 2020
Projected Completion Date: September 2021

Understand how we build parks.

Funding

Total Funding: $2,289,000
Funding Sources:
  • Mayoral
  • Federal

Locations

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 08/12/2020