Tappen Park and South Beach Fountain Repair

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will repair the electrical and mechanical components of three fountains damaged during Hurricane Sandy, including: the decorative fountain at Tappen Park and Fountain of the Dolphins at South Beach.

Project Update: Parks has reviewed bids received for this contract and identified the lowest apparent bidder. Working with external agencies, Parks is now reviewing the bid and the vendor’s qualifications.

Project Timeline

Design

Start Date: July 2015
Projected Completion Date: June 2016
Completion Date: June 2017

Procurement

Start Date: June 2017
Projected Completion Date: March 2018
Adjusted Completion Date: October 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Sources:
  • Mayoral
  • Federal

Locations

 

Project Staff

Project Liaison: Charles Fall
Contact NYC Parks about this project

Last updated: 07/19/2018