Tappen Park and South Beach Fountain Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the electrical and mechanical components of fountains damaged during Hurricane Sandy at Tappen Park and South Beach.
Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.
Project Timeline
Design
Start Date: July 2015
Projected Completion Date:
June 2016
Completion Date:
June 2017
Procurement
Start Date: June 2017
Projected Completion Date:
March 2018
Completion
Date:
February 2020
Construction
Start Date: September 2020
Projected Completion Date:
September 2021
Completion
Date:
May 2022
Understand how we build parks.
Funding
Funding Sources:
- Mayoral
- Federal
Locations
-
Franklin D. Roosevelt Boardwalk and Beach, Staten Island
Father Capodanno Boulevard, Boardwalk, Doty, Avenue, Sea Gate Court -
Tappen Park, Staten Island
Canal Street, Wright to Bay Streets
Project Staff
Project Liaison: Joseph Homsey
Contact NYC Parks
about this project
Last updated: 05/26/2022