Ralph Demarco Park Shoreline Reconstruction (Hurricane Sandy)

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will reconstruct the shoreline damaged by Hurricane Sandy in Ralph Demarco Park.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.

Project Timeline

Design

Start Date: July 2016
Projected Completion Date: September 2017
Completion Date: October 2020

Procurement

Start Date: October 2020
Projected Completion Date: July 2021

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $5 million and $10 million
Funding Sources:
  • Mayoral
  • Federal

Location

Ralph Demarco Park , Queens
East River, Shore Boulevard, Ditmars Boulevard, 20th Avenue

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 12/02/2020