Conference House Park Path, Rail, and Landscape Reconstruction (Hurricane Sandy)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    19% complete

This project will reconstruct Hurricane Sandy-damaged paths, the overlook and the parking lot in Conference House Park.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: May 2015
Projected Completion Date: June 2016
Completion Date: January 2017

Procurement

Start Date: January 2017
Projected Completion Date: October 2017
Completion Date: May 2018

Construction

Start Date: June 2018
Projected Completion Date: June 2019

Understand how we build parks.

Funding

Total Funding: $388,000
Funding Sources:
  • Mayoral
  • Federal

Location

Conference House Park , Staten Island
Page Avenue between Raritan Bay and Hylan Boulevard

 

Project Staff

Project Liaison: Charles Fall
Contact NYC Parks about this project

Last updated: 11/16/2018