Brooklyn General Site Work For Hurricane Sandy (BG-1113M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct play equipment, safety surfacing, athletic fields, pavements, fencing, and masonry at various parks in Brooklyn that were damaged by Hurricane Sandy.

Project Timeline

Design

Start Date: April 2013
Projected Completion Date: July 2013
Completion Date: June 2014

Procurement

Start Date: June 2014
Projected Completion Date: March 2015
Completion Date: June 2015

Construction

Start Date: July 2015
Projected Completion Date: January 2017
Completion Date: December 2016

Understand how we build parks.

Funding

Total Funding: $2,704,000
Funding Sources:
  • Mayoral
  • Federal

Locations

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 09/17/2019