Brooklyn General Site Work For Hurricane Sandy (BG-1113M)
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct play equipment, safety surfacing, athletic fields, pavements, fencing, and masonry at various parks in Brooklyn that were damaged by Hurricane Sandy.
Project Timeline
Design
Start Date: April 2013
Projected Completion Date:
July 2013
Completion Date:
June 2014
Procurement
Start Date: June 2014
Projected Completion Date:
March 2015
Completion
Date:
June 2015
Construction
Start Date: July 2015
Projected Completion Date:
January 2017
Completion
Date:
December 2016
Understand how we build parks.
Funding
Funding Sources:
- Federal
- Mayoral
Locations
-
Brighton Playground, Brooklyn
Brighton 2nd Street & Boardwalk -
Carroll Park, Brooklyn
Court St., Smith St., bet. Carroll St. and President St. -
Coffey Park, Brooklyn
Verona St. bet. Richard St. and Dwight St. -
McGuire Fields, Brooklyn
Ave Y., Bergen Ave. bet. Ave. V and Belt Pkwy. -
Nautilus Playground, Brooklyn
Public Beach, W 29 and W 32 Sts -
Ocean Parkway Malls, Brooklyn
Park Circle To Coney Island Concourse
Project Staff
Project Liaison: Davey Ives