Wingate Park Gym, Heckscher Playground, and Nautilus Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the outdoor gym at Wingate Park, the play area at Heckscher Playground, and the handball, basketball, sitting area and multi-purpose play area at Nautilus Playground.

Project Timeline

Design

Start Date: May 2012
Projected Completion Date: June 2013
Completion Date: August 2013

Procurement

Start Date: August 2013
Projected Completion Date: May 2014
Completion Date: February 2015

Construction

Start Date: April 2015
Projected Completion Date: July 2016
Completion Date: May 2017

Understand how we build parks.

Funding

Total Funding: $1,840,000
Funding Sources:
  • Mayoral
  • City Council

Locations

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/20/2019