NYC Resources311Office of the Mayor

Official Website of the New York City Department of Parks & Recreation

North 5th Street Bulkhead Reconstruction (Hurricane Sandy)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    75% complete

This project will reconstruct the North 5th Street bulkhead in Brooklyn, which was damaged by Hurricane Sandy.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: October 2013
Projected Completion Date: June 2014
Completion Date: January 2016

Procurement

Start Date: January 2016
Projected Completion Date: October 2016
Completion Date: March 2017

Construction

Start Date: October 2017
Projected Completion Date: October 2018

Understand how we build parks.

Funding

Total Funding: $1,775,000
Funding Sources:
  • Mayoral
  • Federal

Location

North 5th Street Pier and Park , Brooklyn
Kent Avenue between North 4th and North 5th Streets, Brooklyn

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 05/21/2018

Was this information helpful?