Staten Island South Emergency Protective Measures (Hurricane Sandy)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct emergency protective measures at Conference House and Crescent Park beaches.

Project Timeline

Design

Start Date: May 2013
Projected Completion Date: June 2013
Completion Date: January 2014

Procurement

Start Date: January 2014
Projected Completion Date: October 2014
Completion Date: November 2013

Construction

Start Date: August 2013
Projected Completion Date: October 2013
Completion Date: December 2013

Understand how we build parks.

Funding

Total Funding: $2,957,000
Funding Sources:
  • Mayoral
  • Federal

Locations

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 11/28/2020