Queens General Site Work (QG-1913M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    54% complete

This multisite contract will reconstruct play equipment, pavements, fencing, water supply, drainage, site features, plantings and general site work in Queens.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: May 2013
Projected Completion Date: October 2013
Completion Date: June 2015

Procurement

Start Date: June 2015
Projected Completion Date: March 2016
Completion Date: July 2016

Construction

Start Date: September 2016
Projected Completion Date: March 2018

Understand how we build parks.

Funding

Total Funding: $794,000
Funding Source: City Council

Locations

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 02/16/2018