Queens General Site Work (QG-1813M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This multisite contract will reconstruct pavements, fencing, water supply, plantings and general site work in Queens.

Project Timeline

Design

Start Date: May 2013
Projected Completion Date: August 2013
Completion Date: August 2013

Procurement

Start Date: August 2013
Projected Completion Date: May 2014
Completion Date: May 2014

Construction

Start Date: October 2014
Projected Completion Date: September 2015
Completion Date: January 2016

Understand how we build parks.

Funding

Total Funding: $571,000