Riverside Drive Bus Stop and Safety Measure Installation

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the bus stops and perimeter sidewalks along Riverside Drive.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: July 2015
Projected Completion Date: March 2015
Completion Date: October 2017

Procurement

Start Date: October 2017
Projected Completion Date: July 2018
Completion Date: January 2019

Construction

Start Date: March 2019
Projected Completion Date: May 2020

Understand how we build parks.

Funding

Total Funding: $2,405,000
Funding Sources:
  • Mayoral
  • Borough President
  • Federal

Location

Riverside Park , Manhattan
Riverside Drive between West 97th Street and West 125th Street

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 03/22/2019