Riverside Drive Bus Stop and Safety Measure Installation

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the bus stops and perimeter sidewalks along Riverside Drive.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: July 2015
Projected Completion Date: March 2015
Completion Date: October 2017

Procurement

Start Date: October 2017
Projected Completion Date: July 2018
Completion Date: January 2019

Construction

Start Date: March 2019
Projected Completion Date: May 2020
Completion Date: October 2020

Understand how we build parks.

Funding

Total Funding: $3,234,000
Funding Sources:
  • Mayoral
  • Borough President
  • Federal

Location

Riverside Park , Manhattan
Riverside Drive between West 97th Street and West 125th Street

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 12/04/2020