Riverside Drive Bus Stop and Safety Measure Installation

  • Design
    90% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct the bus stops and perimeter sidewalks at various locations on Riverside Drive from W97th to W125th streets.

Project Update: All contract documents are now in final review to complete the design process.

Project Timeline

Design

Start Date: July 2015
Projected Completion Date: March 2015
Adjusted Completion Date: October 2017

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Sources:
  • Mayoral
  • Borough President
  • Federal

Location

Riverside Park, Manhattan

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 09/20/2017