Riverside Drive Bus Stop and Safety Measure Installation

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct the bus stops and perimeter sidewalks along Riverside Drive.

Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.

Project Timeline

Design

Start Date: July 2015
Projected Completion Date: March 2015
Completion Date: October 2017

Procurement

Start Date: October 2017
Projected Completion Date: July 2018
Adjusted Completion Date: November 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Sources:
  • Mayoral
  • Borough President
  • Federal

Location

Riverside Park , Manhattan
Riverside Drive between West 97th Street and West 125th Street

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 10/15/2018