Staten Island Emergency Protective Measures (Hurricane Sandy)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct emergency protective measures at FDR Beach and Boardwalk.

Project Timeline

Design

Start Date: January 2013
Projected Completion Date: April 2013
Completion Date: April 2013

Procurement

Start Date: April 2013
Projected Completion Date: January 2014
Completion Date: July 2014

Construction

Start Date: April 2013
Projected Completion Date: October 2013
Completion Date: December 2013