Asser Levy Recreation Center Boiler and Pool Dehumidifier Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the boiler and pool dehumidification system at Asser Levy Recreation Center.

Project Timeline

Design

Start Date: October 2012
Projected Completion Date: August 2013
Completion Date: December 2013

Procurement

Start Date: December 2013
Projected Completion Date: August 2014
Completion Date: January 2015

Construction

Start Date: February 2015
Projected Completion Date: February 2016
Completion Date: May 2017