Queens General Comfort Station and Facility Reconstruction (QG-1513MA1)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    65% complete

This project will reconstruct comfort stations and facilities at various parks and recreation locations in Queens.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: May 2013
Projected Completion Date: May 2013
Completion Date: July 2015

Procurement

Start Date: July 2015
Projected Completion Date: April 2016
Completion Date: March 2017

Construction

Start Date: April 2017
Projected Completion Date: April 2019

Understand how we build parks.

Funding

Total Funding: $1,450,000
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Locations

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 05/21/2018