Queens General Comfort Station and Facility Reconstruction (QG-1413MA)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    89% complete

This project will reconstruct comfort stations and facilities at various parks and recreation locations in Queens.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: April 2013
Projected Completion Date: May 2013
Completion Date: September 2014

Procurement

Start Date: September 2014
Projected Completion Date: June 2015
Completion Date: July 2015

Construction

Start Date: September 2015
Projected Completion Date: September 2017
Adjusted Completion Date: April 2018

Understand how we build parks.

Funding

Total Funding: $1,500,000
Funding Sources:
  • Mayoral
  • Borough President

Locations

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 05/22/2018