O'Connell Playground Recreation Building Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the recreation building in Daniel M. O'Connell Playground.

Project Timeline

Design

Start Date: March 2013
Projected Completion Date: May 2013
Completion Date: December 2013

Procurement

Start Date: December 2013
Projected Completion Date: September 2014
Completion Date: December 2018

Construction

Start Date: October 2018
Projected Completion Date: April 2019
Completion Date: April 2019

Understand how we build parks.

Funding

Total Funding: $1,546,000
Funding Sources:
  • Mayoral
  • City Council

Location

Daniel M. O'Connell Playground , Queens
Murdoch Avenue, 113th Avenues, 196th Street, 197th Street

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 07/19/2019