Staten Island General Site Work (RG-1013M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the basketball courts, pavements, fencing, safety surfacing, timber barrier rails and landscaping elements at various sites in Staten Island.

Project Timeline

Design

Start Date: May 2012
Projected Completion Date: May 2013
Completion Date: July 2013

Procurement

Start Date: July 2013
Projected Completion Date: April 2014
Completion Date: July 2015

Construction

Start Date: July 2015
Projected Completion Date: July 2017
Completion Date: December 2016

Understand how we build parks.

Funding

Total Funding: $2,157,000
Funding Sources:
  • Mayoral
  • City Council

Locations

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 11/25/2020