Staten Island General Site Work (RG-913M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct pavements, fencing and landscaping elements at various parks in Staten Island.

Project Timeline

Design

Start Date: May 2012
Projected Completion Date: May 2013
Completion Date: May 2013

Procurement

Start Date: May 2013
Projected Completion Date: February 2014
Completion Date: December 2013

Construction

Start Date: February 2014
Projected Completion Date: August 2015
Completion Date: August 2015

Understand how we build parks.

Funding

Total Funding: $2,527,000
Funding Sources:
  • Mayoral
  • Borough President
  • Federal

Locations

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 12/12/2019