Queens General Site Work (QG-1313M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    69% complete

This multisite contract will reconstruct play equipment, pavements, fencing, water supply, drainage, site features, plantings and general site work in Queens.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: January 2013
Projected Completion Date: August 2013
Completion Date: October 2014

Procurement

Start Date: October 2014
Projected Completion Date: July 2015
Completion Date: July 2015

Construction

Start Date: November 2015
Projected Completion Date: May 2017
Adjusted Completion Date: October 2017

Understand how we build parks.

Funding

Total Funding: $1,790,000
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Locations

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 11/16/2017