Queens General Site Work (QG-1313M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Frank O'Connor Playground, Crowley Playground, and Real Good Playground.

Project Timeline

Design

Start Date: January 2013
Projected Completion Date: August 2013
Completion Date: October 2014

Procurement

Start Date: October 2014
Projected Completion Date: July 2015
Completion Date: July 2015

Construction

Start Date: November 2015
Projected Completion Date: May 2017
Completion Date: February 2018

Understand how we build parks.

Funding

Total Funding: $1,934,000
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Locations

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 10/18/2019