Queens General Site Work (QG-913M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This multisite contract will reconstruct pavements, drainage, plantings, safety surface and general site work in Queens.

Project Timeline

Design

Start Date: January 2013
Projected Completion Date: May 2013
Completion Date: August 2013

Procurement

Start Date: August 2013
Projected Completion Date: May 2014
Completion Date: June 2014

Construction

Start Date: September 2014
Projected Completion Date: March 2016
Completion Date: July 2015

Understand how we build parks.

Funding

Total Funding: $1,178,000
Funding Source: Borough President

Locations

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 11/27/2020