Staten Island General Site Work (RG-713M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This multisite contract will reconstruct play equipment, safety surfacing, play fields, pavements, fencing, plantings and general site work at various sites in Staten Island.

Project Timeline

Design

Start Date: March 2012
Projected Completion Date: March 2013
Completion Date: March 2013

Procurement

Start Date: March 2013
Projected Completion Date: December 2013
Completion Date: September 2013

Construction

Start Date: October 2013
Projected Completion Date: April 2015
Completion Date: March 2015

Understand how we build parks.

Funding

Total Funding: $1,119,000
Funding Sources:
  • Mayoral
  • Federal

Locations

 

Project Staff

Project Liaison: Charles Fall
Contact NYC Parks about this project

Last updated: 09/18/2017