Tiffany Street Pier Reconstruction (Hurricane Sandy)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the fishing pier that was damaged by Hurricane Sandy.

Project Timeline

Design

Start Date: August 2013
Projected Completion Date: March 2015
Completion Date: October 2015

Procurement

Start Date: October 2015
Projected Completion Date: July 2016
Completion Date: March 2017

Construction

Start Date: April 2017
Projected Completion Date: April 2018
Completion Date: April 2018

Understand how we build parks.

Funding

Total Funding: $1,915,000
Funding Sources:
  • Mayoral
  • Federal

Location

Tiffany Street Pier , Bronx
Tiffany Street pier located at East river and intersection Tiffany Street and Viele Avenue, Bronx N.Y.

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 08/17/2018