Shoelace Park Green Infrastructure Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct green infrastructure to capture storm water and stabilize hillsides and slopes at Shoelace Park.

Project Timeline

Design

Start Date: March 2012
Projected Completion Date: June 2014
Completion Date: February 2016

Procurement

Start Date: February 2016
Projected Completion Date: November 2016
Completion Date: March 2017

Construction

Start Date: July 2017
Projected Completion Date: July 2018
Completion Date: July 2018

Understand how we build parks.

Funding

Total Funding: $339,000
Funding Source: Federal