Bronx River Watershed Green Infrastructure Construction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will construct green infrastructure to capture storm water at various sites within the Bronx River watershed.

Project Update: The project is currently in legal review by staff members at Parks and the New York City Corporation Counsel.

Project Timeline

Design

Start Date: March 2013
Projected Completion Date: January 2014
Completion Date: March 2018

Procurement

Start Date: March 2018
Projected Completion Date: December 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: Mayoral

Location

Bruckner Blvd, Soundview Ave, Rosedale Ave, Watson Ave, Gleason Ave, Story Ave, Morrison Ave, Stratford Ave, Westchester Ave, Fteley Ave, Commonwealth Ave, Noble Ave, East 172-173rd Sts, Beach Ave, Bronx River Ave, Manor Ave

Project Staff

Contact NYC Parks about this project

Last updated: 05/21/2018