Tony Dapolito Recreation Center and John Jay Pool Boiler Systems Reconstruction (Hurricane Sandy)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct boiler components damaged by Hurricane Sandy at Tony Dapolito Recreation Center and John Jay Pool.

Project Timeline

Design

Start Date: December 2012
Projected Completion Date: February 2013
Completion Date: March 2013

Procurement

Start Date: March 2013
Projected Completion Date: December 2013
Completion Date: May 2014

Construction

Start Date: June 2014
Projected Completion Date: June 2015
Completion Date: February 2015

Understand how we build parks.

Funding

Total Funding: $1,968,000