Manhattan General Site Work (MG-213M)

  • Design
    100% complete 
  • Procurement
    100% complete 
  • Construction
    75% complete 

This project will reconstruct pavements, fences, plantings, plumbing and general site work in Manhattan.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: March 2013
Projected Completion Date:May 2014
Completion Date: June 2014

Procurement

Start Date: June 2014
Projected Completion Date:March 2015
Completion Date: June 2015

Construction

Start Date: June 2015
Projected Completion Date:December 2016

Understand how we build parks.

Funding

Total Funding: $929,000
Funding Source:City Council

Locations

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 01/13/2017