Manhattan General Site Work (MG-213M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct pavements, fences, plantings, plumbing and general site work in Manhattan.

Project Timeline

Design

Start Date: March 2013
Projected Completion Date: May 2014
Completion Date: June 2014

Procurement

Start Date: June 2014
Projected Completion Date: March 2015
Completion Date: June 2015

Construction

Start Date: June 2015
Projected Completion Date: December 2016
Completion Date: December 2016

Understand how we build parks.

Funding

Total Funding: $1,059,000
Funding Source: City Council

Locations

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/25/2020