Citywide Sandy-Related Recreational Lighting and Electrical Line Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct recreational lighting and overhead electrical lines due to Hurricane Sandy at various parks locations citywide.

Project Timeline

Design

Start Date: December 2012
Completion Date: March 2013

Procurement

Start Date: March 2013
Projected Completion Date: December 2013
Completion Date: May 2013

Construction

Start Date: February 2013
Projected Completion Date: June 2013
Completion Date: November 2013

Understand how we build parks.

Funding

Total Funding: $373,000
Funding Sources:
  • Federal
  • Mayoral