CS 134 Community Garden Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    51% complete

This project will reconstruct the perimeter concrete retaining walls, steel fencing and gate, and install a new water supply system at CS 134 Community Garden.

Due to COVID related construction industry impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: March 2017
Projected Completion Date: July 2017
Completion Date: June 2018

Procurement

Start Date: June 2018
Projected Completion Date: March 2019
Completion Date: March 2019

Construction

Start Date: May 2019
Projected Completion Date: May 2020

Understand how we build parks.

Funding

Total Funding: $775,000
Funding Source: City Council

Location

Bristow Street between Freeman and Jennings Streets

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 06/01/2020