NYC Resources311Office of the Mayor

Official Website of the New York City Department of Parks & Recreation

CS 134 Community Garden Reconstruction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct the perimeter concrete retaining walls, steel fencing and gate, and install a new water supply system at CS 134 Community Garden.

Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.

Project Timeline

Design

Start Date: March 2017
Projected Completion Date: July 2017
Completion Date: August 2017

Procurement

Start Date: August 2017
Projected Completion Date: April 2018
Adjusted Completion Date: November 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: City Council

Location

Bristow Street between Freeman and Jennings Streets

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 05/24/2018

Was this information helpful?