CS 134 Community Garden Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    53% complete

This project will reconstruct the perimeter concrete retaining walls, steel fencing and gate, and install a new water supply system at CS 134 Community Garden.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: March 2017
Projected Completion Date: July 2017
Completion Date: June 2018

Procurement

Start Date: June 2018
Projected Completion Date: March 2019
Completion Date: March 2019

Construction

Start Date: May 2019
Projected Completion Date: May 2020
Adjusted Completion Date: August 2021

Understand how we build parks.

Funding

Total Funding: $1,014,000
Funding Sources:
  • Mayoral
  • City Council

Location

Bristow Street between Freeman and Jennings Streets

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 06/20/2021

Was this information helpful?