Red Hook Recreation Center Sandy-Related Boiler Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project is for the emergency reconstruction of the boiler at the Red Hook Recreation Center.

Project Timeline

Design

Start Date: December 2012
Completion Date: February 2013

Procurement

Start Date: February 2013
Projected Completion Date: November 2013
Completion Date: July 2013

Construction

Start Date: June 2013
Projected Completion Date: October 2013
Completion Date: June 2014

Understand how we build parks.

Funding

Total Funding: $714,000
Funding Sources:
  • Mayoral
  • Federal

Location

Red Hook Recreation Area , Brooklyn
Bay Street between Clinton and Henry Streets, Brooklyn

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 07/19/2019