Whalen Park Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    67% complete

This project will reconstruct Whalen Park in the Bronx.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: January 2013
Projected Completion Date: May 2015
Completion Date: December 2015

Procurement

Start Date: December 2015
Projected Completion Date: September 2016
Completion Date: April 2017

Construction

Start Date: June 2017
Projected Completion Date: June 2018

Understand how we build parks.

Funding

Total Funding: $1,633,000
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

Whalen Park , Bronx
Perry Avenue and East 205th Street

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 05/24/2018