Crotona Park Ballfield 5 Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct field #5 with artificial turf.

Project Update: The contract is registered.

Project Timeline

Design

Start Date: April 2016
Projected Completion Date: April 2017
Completion Date: June 2017

Procurement

Start Date: June 2017
Projected Completion Date: March 2018
Completion Date: June 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

Crotona Park , Bronx
Crotona Park at Crotona Park North and Crotona Avenue

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 06/22/2018