Parque de los Ninos Playground and Seating Area Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the playground and seating area at Parque de los Ninos.

Project Timeline

Design

Start Date: December 2013
Projected Completion Date: June 2015
Completion Date: July 2015

Procurement

Start Date: July 2015
Projected Completion Date: April 2016
Completion Date: September 2016

Construction

Start Date: August 2016
Projected Completion Date: July 2017
Completion Date: March 2017

Understand how we build parks.

Funding

Total Funding: $1,496,000
Funding Sources:
  • Borough President
  • Mayoral

Location

Bronx River Parkway , Bronx
Morrison Avenue and Watson Avenue

 

Project Staff

Project Liaison: Mike Ortiz
Contact NYC Parks about this project

Last updated: 10/04/2022