Idlewild Park Fencing, Sidewalks and Parking Lot Reconstruction
-
100% complete
-
60% complete
-
0% complete
This project will reconstruct the fencing, sidewalks and parking lot at Idlewild Park.
Project Update: Parks has reviewed bids received for this contract and identified the lowest apparent bidder. Working with external agencies, Parks is now reviewing the bid and the vendor’s qualifications.
Project Timeline
Design
Start Date: November 2018
Projected Completion Date:
April 2020
Completion Date:
November 2020
Procurement
Start Date: November 2020
Projected Completion Date:
August 2021
Adjusted Completion
Date:
January 2023
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Idlewild Park
, Queens
Rockaway Boulevard and Brookville Boulevard
Project Staff
Project Liaison: Mike Dockett
Contact NYC Parks
about this project
Last updated: 08/18/2022