Idlewild Park Fencing, Sidewalks and Parking Lot Reconstruction

  • Design
    100% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct the fencing, sidewalks and parking lot at Idlewild Park.

Project Update: The design completion date has changed. Some of the common reasons why a completion date has changed are: scope and funding are added to a project, design changes due to comments from other government agencies and the public, design changes due to field conditions found during site testing and/or issues with a design consultant.

Project Timeline

Design

Start Date: November 2018
Projected Completion Date: April 2020
Completion Date: November 2020

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: Mayoral

Location

Idlewild Park , Queens
Rockaway Boulevard and Brookville Boulevard

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 11/25/2020