St. Mary's Park and Recreation Center Green Infrastructure Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    86% complete

This project will construct rain gardens and other green infrastructure to capture storm water at St. Mary's Park in the Bronx.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: July 2014
Projected Completion Date: May 2015
Completion Date: September 2017

Procurement

Start Date: September 2017
Projected Completion Date: June 2018
Completion Date: November 2018

Construction

Start Date: January 2019
Projected Completion Date: January 2020

Understand how we build parks.

Funding

Total Funding: $1,458,000
Funding Sources:
  • Mayoral
  • State

Location

St. Mary's Park , Bronx
St. Anns Avenue between East 145th and East 146th Streets

 

Project Staff

Contact NYC Parks about this project

Last updated: 10/22/2019