St. Mary's Park and Recreation Center Green Infrastructure Construction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will construct rain gardens and other green infrastructure to capture storm water at St. Mary's Park in the Bronx.

Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.

Project Timeline

Design

Start Date: July 2014
Projected Completion Date: May 2015
Completion Date: September 2017

Procurement

Start Date: September 2017
Projected Completion Date: June 2018
Adjusted Completion Date: October 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Sources:
  • Mayoral
  • State

Location

St. Mary's Park , Bronx
St. Anns Avenue between East 145th and East 146th Streets

 

Project Staff

Contact NYC Parks about this project

Last updated: 08/10/2018