Flushing Meadows Corona Park Synthetic Turf Field 1 Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will replace the deteriorated field using the latest in synthetic turf technology.

Project Timeline

Design

Start Date: February 2012
Projected Completion Date: May 2013
Completion Date: July 2013

Procurement

Start Date: July 2013
Projected Completion Date: April 2014
Completion Date: July 2014

Construction

Start Date: September 2014
Projected Completion Date: September 2015
Completion Date: July 2015

Understand how we build parks.

Funding

Total Funding: $693,000
Funding Source: City Council

Location

Flushing Meadows Corona Park, Queens
Fountain of the Fairs, Flushing Meadows-Corona Park, Queens

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 11/20/2017