Little Bay Park Soccer Fields Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the natural turf soccer fields at Little Bay Park.

Project Timeline

Design

Start Date: April 2014
Projected Completion Date: October 2014
Completion Date: April 2015

Procurement

Start Date: April 2015
Projected Completion Date: January 2016
Completion Date: December 2015

Construction

Start Date: April 2016
Projected Completion Date: April 2017
Completion Date: May 2017