Forest Park T-Ball Field and The Overlook Drainage System Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the paths, drainage and the T-ball field in Forest Park.

Project Timeline

Design

Start Date: February 2013
Projected Completion Date: November 2013
Completion Date: February 2014

Procurement

Start Date: February 2014
Projected Completion Date: November 2014
Completion Date: January 2015

Construction

Start Date: June 2015
Projected Completion Date: June 2016
Completion Date: June 2016

Understand how we build parks.

Funding

Total Funding: $1,361,000
Funding Sources:
  • Borough President
  • City Council

Location

Forest Park, Queens
Park Lane between Union Turnpike and Park Lane South, Queens

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 11/16/2017