Forest Park T-Ball Field and The Overlook Drainage System Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the paths, drainage and the T-ball field in Forest Park.
Project Timeline
Design
Start Date: February 2013
Projected Completion Date:
November 2013
Completion Date:
February 2014
Procurement
Start Date: February 2014
Projected Completion Date:
November 2014
Completion
Date:
January 2015
Construction
Start Date: June 2015
Projected Completion Date:
June 2016
Completion
Date:
June 2016
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Location
Forest Park
, Queens
Park Lane between Union Turnpike and Park Lane South, Queens
Project Staff
Project Liaison: Mike Dockett
Contact NYC Parks
about this project